Friday, April 24, 2015

general updates as at 25/4/15

time to update our beloved residents concerning the happening in Vista Condo...

1) the job for replacing the faulty under ground conceal main pipe at blk k parking area already completed, it took abt one week to finish, now we are monitoring the water flow rate at the main drain besides the blk k, the full payment will be made only after we are sure that the job is indeed done properly.

2) new office clerk Ishak has reported to work, he is replacing the the previous clerk Ah Lai, hope he is an efficient worker, just for resident's info, another veteran staff Mr Rahman's role is building supervisor, so most of the time he will check on our common area, attends to residents' complaint, also to monitor the work of other vendor like guards, housekeeping staffs, renovators, etc.

3) we have sent the letters to all the unit owner of the foreigners hostel to ask them not to convert their unit to be hostel and if they insist then new rate of service charge RM500 will be imposed starting May 2015, so far some of them responded & still negotiating of moving out the tenants but most of them just don't bother, well, let's see how it goes in May....

4) some residents suggested in the previous posts that should put the defaulters' unit number & outstanding amount at the notice board (or other places which many peoples will pass by), we thought this this is workable idea, so from next month onward, defaulters' detail will be up at the notice board at every middle of the month, hope this will create some pressure for them to pay SC promptly.

thanks.


5 comments:

Anonymous said...

Hi,

Please send me the insurance policy to my email as below:
qwe85rty85@yahoo.com.my
Thanks.

Management Corporation :- said...

hi,

have contacted policy provider to send us the soft copy, once got it will forward it to u immediately, should be early next week, thanks.

regards.

Anonymous said...

Hi MC,
For my opinion I would like suggest to increase their service RM500 to RM1000 because most of the company will pay their rental very high. Our place is residential area NOT hostel. We leaving here as family not like bujang.Please consider.

TQ

Anonymous said...

Hi Mr. Cheng & Committee

Can you check the corridor lighting at block K 9th floor front of lifts..its have being dark for 1 week already..

Thx.

Management Corporation :- said...

hi,

will get office to into the light problem at 9th floor...

concerning to increase further SC for the foreigner hostel, actually committee also feel the same, the next AGM will be in another few months' time, let's see how other residents will look at this, thanks.

best regards.