Friday, January 23, 2015

new water tanks in sight :)

lastly, lastly, lastly, we have got the letter from Jabatan Kewangan Negeri to confirm on the water tanks!

on THURSDAY we have received a phone call from the department, ask us if we want them to send the letter to us or we will drop by Komtar to collect from them (as earlier on we have told them to call us once the letter is ready), without second thought we asked them to keep the letter for us & we will go there on the same day to take from them, so after the long wait, we have seen the letter on that day!

in fact the deal is much better than what we first expected, we must thank God for His help, also thank the state gov't for their generosity...., the proposal they have picked for us is for 10 new water tanks, fiber glass type, total cost is RM405K, wow!!!!

out of this 405K, 80% or RM324K will borne by state govt, whereas 20% or 81K will need to be paid thru management fund, for this is the arrangement for low medium cost apartment (LMC) project funded by state gov't, it's got be based on 80% / 20% arrangement.

(we are fortunate enough to be considered as LMC apartment, as the first selling price by the developer those days was RM80K, which qualifies us to be LMC, many apartments in the neighborhood can't be considered as LMC, which make it very very very difficult to get the state gov't to fund projects like us,we also want to thank God for this LMC status. yeah must thank YB Yeoh Soon Hin too, because he also helped to send a letter to the kewangan to confirm Vista Condo is a LMC project)

concerning the 20% or 81K which to be borne by Vista Condo, we have talked to the contractor who is chosen to handle this project, he is willing to let us trade in our existing 10 water tanks (blk j roof top 4x, blk k roof top 4x, blk j pump room 1x, blk k pump 1x) to him with the price very close to RM80K, and the best is that he will try as much as possible to pay us in advance some big portion of the money so that we are able to get the bank to issue banker cheq for 81K, because by procedure we need to deposit this 20% into the state treasury for them to issue the work order to the contractor, but all these proposal must be approved by the MC in this coming meeting, haha...! hope that no one will object this :P

so....., even now we are still very happily digesting this piece of great news, and thank God for His favor upon Vista Condo....







8 comments:

Anonymous said...

Hi Mr. Cheng & Committee

Firstly Want To Thanks You All For The Hard Work Done (Lift & now Water Supply Tanks)...

May I Ask This Upgrade Does It's Including The pipping to our individual units as well??As I Notice most of it already rusted and leaked...

Another concerning / Busybody Owner..Thx.

KK said...

I think we should thanks God and also our beloved MC.

BIG THANK YOU!

Management Corporation :- said...

hi,

thanks for all the kind words.

this round we are just to change the water tanks but not the common pipes as mentioned in the comment, perhaps in the future we will try to ask them to fund this project too.

thanks & regards.

Anonymous said...

hi,MC,

It was noticed tat some defaulters who still not paid up their outstanding (maint fees) can easily get into Vista condo by scanning their access card/motor tag.It was suspected tat they're using duplicate access card as some banner shop in Pg tat provided back-up existing or original proximity card
to another card .kindly pls look into tis problem,its unfair to those good pay master.thx you...

Anonymous said...

Dear Committee,

Just need to clarify on construction n drilling works taking place at the apartment, the last i knew was that the drilling is only allowed to take place during working hours between 9am - 5 pm on weekdays. Is there a change in this ruling as the drilling at J block, 9th floor which has been going on since Dec last year is sometimes going on Saturdays and today it appears to be going on even after 5pm. Please advice.

Management Corporation :- said...

hi,

thanks for all the feedback, abt the duplicated T&G cards, we did catch a few & blocked them, but afraid still some cards still can't detect & manage to come in, if u don't mind pls either email us or give their unit number to us, thanks.

concerning the renovation, it's strictly 9am to 5pm, we have just told management staffs (today) from now on must make sure all renovation work must stop by 5pm, by visiting those unit undergoing renovation at 5pm to ask the worker to go home immediately, pls write to us if happen again.

best regards.

Anonymous said...

Hi,

The drilling and hacking on 9th floor (J block) was still going on after 5pm today (28/01. Although the management may still be in the midst of informing the contractors as we just brought up this issue yday i thought it would be right to notify you that it was still ongoing today.

Management Corporation :- said...

hi,

we too, felt very upset with the renovator & hv asked the guard & office staffs to stop them from coming in anymore, we will also hold back the renovation deposit as this unit have been violating many rules since they started their works many months ago.

thanks.